Modine Starts Airedale Chiller Production at 682,000-Square-Foot Texas Plant
The Grand Prairie plant has one line and one shift running. Modine is aiming for four 2 MW chiller lines there by the end of its fiscal year on March 31.
Modine has begun commercial production of Airedale chillers at a 682,000-square-foot plant in Grand Prairie, Texas, the Racine, Wis., company said Nov. 11. The plant builds 2 MW and 3 MW chillers with free cooling for data center customers, and Modine expects it to become the largest Airedale chiller factory in its global network.
The first production line started this month. Modine is targeting four operational 2 MW lines by the end of its fiscal year on March 31, "subject to equipment commissioning, workforce readiness, and other operational considerations," according to the release, and the plant runs one shift now with plans to move to three.
"Scaling our capacity close to our customers enables us to partner with them to deliver the right highly engineered cooling solutions to help them advance their progress and achieve their performance objectives," President and CEO Neil D. Brinker said.
Later Than the City's First Timetable
The City of Grand Prairie announced the project in October 2025, putting the plant at 2100 Refuge Way and promising more than 1,000 jobs at an average annual wage of $66,760. The city said groundbreaking was planned for the fourth quarter of 2025 and operations for the first quarter of 2026. Cooling Post places the site in Wildlife Commerce Park, between Dallas and Fort Worth.
The plant belongs to a $100 million program Modine announced in July 2025, to be spent over 12 to 18 months at four sites: a new facility in the Dallas area, an expansion in Grenada, Miss., and the possible conversion of former Performance Technologies plants in Franklin, Wis., and Jefferson City, Mo.
Why This Matters to Contractors
Modine's Nov. 4 earnings presentation counted 13 active chiller lines in North America and a plan for 20 by March 31, the same deadline set for Grand Prairie's four 2 MW lines. The company has not said how many of the 20 sit in Texas, but four there would equal more than half of the seven still to come.
Sources
- Modine, "Production of Airedale Chillers for Data Center Customers Begins at New Texas Facility," Nov. 11, 2026. prnewswire.com
- Modine Manufacturing, "Second Quarter Fiscal 2027" earnings presentation, Nov. 4, 2026 (SEC Exhibit 99.2). sec.gov
- City of Grand Prairie, "Modine Expansion to Bring More than 1,000 Jobs to Grand Prairie," Oct. 15, 2025, via Texas Economic Development Council. texasedc.org
- Airedale by Modine, "Modine Announces New $100 Million Investment to Expand Capacity for North American Data Center Business," July 29, 2025. airedale.com
- Cooling Post, "Modine opens Airedale chiller plant in Texas," Nov. 12, 2026. coolingpost.com