R-410A VRF Systems Must Be Fully Charged and Running Before Jan. 1

EPA's May rewrite freed older split-system stock from its install deadline but declined, in its own words, to touch VRF.

Key TakeawayNew R-410A VRF systems with all specified components made or imported before Jan. 1, 2026, can be installed only before Jan. 1, 2027, unless a building permit issued before Oct. 5, 2023, names the refrigerant, which extends the date one year. EPA defines installation as a completed, fully charged circuit ready for use, so a set but uncharged system on Dec. 31 does not qualify.

Most new variable refrigerant flow systems running R-410A have to be installed before Jan. 1, 2027, which leaves 43 days from Nov. 18, and the federal definition of "install" sets a higher bar than setting equipment on a roof. Under 40 CFR 84.52, to install means "to complete a field-assembled system's circuit, including charging with a full charge, such that the system can function and is ready for use for its intended purpose." A VRF job with outdoor units landed and indoor units hung but no refrigerant in the piping on Dec. 31 has not met it.

Environment+Energy Leader revisited the deadline in a Nov. 18 explainer. HAN read the regulation and the two rulemakings behind it.

Two Dates and a Permit Test

The current text of 40 CFR 84.54(c)(2) restricts new VRF systems using refrigerants with a GWP of 700 or greater from Jan. 1, 2026. R-410A, at 2,088, is covered, and R-32, at 675, is not. Such systems "may be installed prior to January 1, 2027, where all specified components of that system are manufactured or imported prior to January 1, 2026." EPA's definition of specified components for this sector is condensing units, condensers, compressors, evaporator units and evaporators.

A later date applies when "an approved building permit issued prior to October 5, 2023, specifies the use of a restricted regulated substance" in the system that permit details, with the same component cutoff. Those projects have until Jan. 1, 2028. In the December 2024 rule that created this allowance, EPA said it considers a building permit to include the designs submitted with the application and approved by the authority having jurisdiction, which matters on jobs where the permit itself names no refrigerant.

By that 2024 rule's description, the VRF restriction reaches air-source VRF systems of 65,000 Btu/h or more and water-source VRF of any capacity. EPA estimated about 42,000 VRF units of 65,000 Btu/h or more were sold in 2023, 0.49 percent of air conditioning and heat pump equipment sales that year, and about 79,000 units across all capacities.

EPA Moved the Date Once and Declined Twice

The original 2023 Technology Transitions rule set the VRF installation date at Jan. 1, 2026. EPA proposed a one-year extension in June 2024 after manufacturers and distributors warned of stranded inventory, held a public hearing that August and published the final rule on Dec. 12, 2024, effective Jan. 13, 2025. Stakeholders told the agency that even the 2027 date "could still risk stranding VRF equipment for larger buildings," which produced the permit allowance.

The Air Conditioning Contractors of America asked for more in comments filed Nov. 21, 2025, urging EPA to give VRF and VRV systems the same relief it was proposing for split systems. ACCA argued that VRF jobs run on construction schedules and carry higher capital costs, with installation dates that depend on factors outside contractor control. When EPA finalized its rewrite on May 26, 2026, it answered that it "did not propose and is not extending the installation date for VRF equipment" and treated the requests as "out of scope for this rulemaking." It pointed to the earlier extensions and to the much smaller number of VRF units held in inventory. The split-system changes from that rule are covered in HAN's Nov. 4 explainer, which also notes New York's earlier Jan. 1, 2026, date under Part 494.

EPA's sector table, last updated Aug. 28, 2026, still lists Jan. 1, 2027, for VRF. Environment+Energy Leader reported that none of the court petitions filed against the May rule targets the VRF dates.

R-32 Lines Bring Their Own Install Work

Mitsubishi Electric Trane HVAC US said in October 2025 that a commercial VRF line using R-32 would reach selected markets in early 2026, and that it would keep supplying R-410A VRF through the first half of 2026. Its announcement describes indoor-unit sensors that detect a leak and automatically stop refrigerant flow to connected indoor units. "R-32 offers a balance of efficiency and reduced environmental impact," said David Archer, the company's vice president of commercial business. Because R-32 is an A2L, a project that switches refrigerants partway through generally goes back to the engineer to check charge limits against the smallest occupied rooms served.

Why This Matters to Contractors

A multi-floor VRF job with dozens of indoor units needs piping complete, pressure tested, evacuated and fully charged before the calendar turns. Contractors holding late R-410A jobs should pull the manufacture or import dates for every condensing unit and evaporator now, since a single indoor unit built after Jan. 1, 2026, breaks the component test for the whole system. Jobs that miss the date face a redesign around R-32 or a hunt for the original permit file to see whether the 2028 allowance applies.

Sources

  1. Code of Federal Regulations, 40 CFR 84.54, restrictions on the use of hydrofluorocarbons, current text. ecfr.gov
  2. Code of Federal Regulations, 40 CFR 84.52, definitions for subpart B, current text. ecfr.gov
  3. U.S. Environmental Protection Agency, "Phasedown of Hydrofluorocarbons: Restrictions on the Use of HFCs Under the AIM Act in Variable Refrigerant Flow Air Conditioning Subsector," 89 FR 100381, Dec. 12, 2024. govinfo.gov
  4. U.S. Environmental Protection Agency, "Phasedown of Hydrofluorocarbons: Reconsideration of Certain Regulatory Requirements Promulgated Under the Technology Transitions Provisions of the AIM Act," 91 FR 31284, May 26, 2026. govinfo.gov
  5. U.S. Environmental Protection Agency, "Technology Transitions HFC Restrictions by Sector," last updated Aug. 28, 2026. epa.gov
  6. ACCA, "ACCA comments back EPA installation deadline removal, push for VRF relief," November 2025. hvac-blog.acca.org
  7. Mitsubishi Electric Trane HVAC US, "METUS Announces New Low-GWP VRF Line Using R-32 Refrigerant for Commercial Applications," October 2025. mitsubishicomfort.com
  8. Environment+Energy Leader, "EPA Left One Refrigerant Deadline Standing for Buildings," Nov. 18, 2026. environmentenergyleader.com
Refrigerants > A2L TransitionR-410AVRFEPATechnology TransitionsAIM ActR-32A2LBuilding PermitsMETUSACCACommercial HVACHeat Pumps